1. LINE

      Text:AAAPrint
      Economy

      Delays, cost overruns jeopardize HK-Guangzhou rail link

      1
      2015-08-11 09:58Global Times Editor: Li Yan

      In April 2014, MTR Corp (MTR), overseeing construction of the Hong Kong leg of the Guangzhou-Shenzhen-Hong Kong Express Rail Link (XRL), announced that the HK$65 billion ($8.38 billion) project would be delayed by several years and run massively over budget. MTR attributed the delay to unexpected construction conditions, tunnel excavation challenges, tight construction times, low "construction efficiency" and a labor shortage. Since the announcement, the Hong Kong authorities and MTR have been casting blame at each other over the delay and budget overrun, leaving taxpayers on the hook for the estimated HK$20.3 billion needed to complete the project. Because the Hong Kong legislature still needs to approve the funding, the project's future is now uncertain.

      It was supposed to be done by now.

      The 26-kilometer section of Guangzhou-Shenzhen-Hong Kong Express Rail Link (XRL) in Hong Kong had been scheduled to be completed on August 4, 2015.

      But in April 2014, MTR Corp (MTR), the company overseeing construction of the rail link, announced that the HK$65 billion ($8.38 billion) project would not only be delayed by several years, but also run massively over budget.

      It took more than a year for MTR to draw up a new plan for the XRL. In late June, the company submitted it to the Hong Kong Special Administrative Region government.

      The plan said that construction wouldn't be completed until the third quarter of 2018 and would cost an additional HK$20.3 billion. It cited complex construction conditions, low "construction efficiency," and a shortage of labor as the reasons for the delay and cost overrun.

      The Hong Kong government is currently reviewing MTR's updated plan for the Hong Kong section, Su Wenjie, deputy general manager of the company's communications department, said in an e-mail sent to the Global Times on Friday.

      The Hong Kong leg of the XRL is a prestige project for the city and its government, which is paying for it. The XRL will run 140 kilometers to Guangzhou, capital of South China's Guangdong Province, passing through the cities of Shenzhen and Dongguan, both in the same province.

      When completed, it will allow a passenger in Hong Kong to travel to Guangzhou in just under 50 minutes, about half the time of a current train ride.

      The Hong Kong SAR government expects the XRL will bear economic dividends and boost local tourism.

      But the project's future is now in jeopardy as it requires the Legislative Council of the Hong Kong Special Administrative Region to approve the additional funding.

      And that's no simple task, said Li Nansheng, a professor at the College of Civil Engineering at Tongji University.

      "In Hong Kong, with its robust legal system, it is a big issue to spend taxpayers' money," he said. "The complex legal system may make it impossible to resolve the dispute in just two or three years."

      A delay in funding is no small matter as it could result in further delays. "The subsequent construction work will be adversely affected if not enough extra money is injected," Li told the Global Times on Friday.

      Reasons for the delay

      Construction on the XRL Hong Kong section began in April 2010 after Hong Kong's Legislative Council approved the project in January that year.

      Under the original timetable, the rail line was supposed to start transporting passengers by the end of 2015.

      When MTR announced the project would be delayed, it surprised the public, the Shanghai-based news website jiemian.com reported on August 5.

      The announcement was notable because it was the first time the company had mentioned anything about delays in the four years since it started, the report said.

      Construction was 68.7 percent completed as of late March, with three sections of the project significantly behind schedule, according to a document MTR submitted to the Legislative Council in June. Overall construction costs were also running 31.23 percent above the original budget.

      MTR attributed the delay to unexpected construction conditions, tunnel excavation challenges, tight construction times, low "construction efficiency" and a labor shortage, according to several documents it submitted to the Hong Kong government.

      The company said that it had established an independent board of directors to review the project and unearth problems.

      "There can be quite a few reasons for construction delays, such as geological conditions, environmental issues, construction management problems as well as other episodic factors," said Li, the Tongji University professor.

      "The XRL Hong Kong section is not a special case," he said. On the Chinese mainland, many railway projects also suffer delays with cost overruns.

      Li's opinion was echoed by Zhang Lingxiang, general manager of the Shanghai Metro's transportation management center.

      "It is hard to absolutely confirm the completion date in the early stages of construction because so many unforeseen issues will emerge in the years it takes to finish a project," Zhang told the Global Times on Friday.

      Zhang also questioned whether the original timetable and budget for the project were reasonable.

      Although MTR has tried to highlight the technical challenges of the project, Li doesn't see them as the major problem.

      "It's not so hard to build underground in Hong Kong due to the environment there and the advanced construction techniques we have nowadays," he said.

      Issues of responsibility

      Some experts see the construction model as the main reason for the delay. The Hong Kong government commissioned MTR in January 2010 to oversee construction of the project. Their agreement gives the government ownership of the project's asset, but the government has to cover the construction costs and bear the construction risks. MTR's role is only supervisory.

      The problem with this model is that it makes it hard to nail down which party is accountable for the delay. Each can cast the blame on the other.

      Both the Hong Kong local government and MTR have refused to take responsibility for the delays and cost overruns, according to media reports. The government said MTR is to blame because it is running the project and is responsible for keeping costs under control, according to the report from jiemian.com.

      However, the agreement stipulates that the government owns the project and must bear the risks of delays and other problems.

      Regardless of which party is actually responsible for the delays, Hong Kong taxpayers are the ones footing the bill. After all, the government owns 76 percent of the company, jiemian.com reported, citing experts.

      MTR needs the additional HK$20.3 billion to pay for the extended construction period, revise parts of the project and backup funding, according to a document the company submitted to the Legislative Council in June.

      For its part, MTR has the same goal as the government, which is to complete the project as soon as possible, within budget, Su said.

        

      Related news

      MorePhoto

      Most popular in 24h

      MoreTop news

      MoreVideo

      News
      Politics
      Business
      Society
      Culture
      Military
      Sci-tech
      Entertainment
      Sports
      Odd
      Features
      Biz
      Economy
      Travel
      Travel News
      Travel Types
      Events
      Food
      Hotel
      Bar & Club
      Architecture
      Gallery
      Photo
      CNS Photo
      Video
      Video
      Learning Chinese
      Learn About China
      Social Chinese
      Business Chinese
      Buzz Words
      Bilingual
      Resources
      ECNS Wire
      Special Coverage
      Infographics
      Voices
      LINE
      Back to top Links | About Us | Jobs | Contact Us | Privacy Policy
      Copyright ©1999-2018 Chinanews.com. All rights reserved.
      Reproduction in whole or in part without permission is prohibited.
      主站蜘蛛池模板: 久久亚洲国产成人影院网站| 国产美女无遮挡免费视频| 中文字幕版免费电影网站| 未满十八18禁止免费无码网站 | 亚洲日韩人妻第一页| 女bbbbxxxx另类亚洲| 日本高清免费观看| 亚洲va无码专区国产乱码| 国产一精品一av一免费爽爽| 亚洲国产精品va在线播放| 久久免费区一区二区三波多野| 亚洲av无码专区国产乱码在线观看 | 最近中文字幕mv免费高清电影| 亚洲成AⅤ人影院在线观看| 亚洲美女视频一区| 久久久久久精品成人免费图片 | 亚洲乱码av中文一区二区| 成人A毛片免费观看网站| 亚洲美女又黄又爽在线观看| 无码国产精品一区二区免费式芒果| 亚洲高清在线播放| 九九精品免费视频| 亚洲精品色在线网站| 久久影院亚洲一区| 91九色老熟女免费资源站| 亚洲永久网址在线观看| 最近中文字幕免费完整| 亚洲精品无码久久千人斩| 特级精品毛片免费观看| 亚洲入口无毒网址你懂的| 国产免费黄色大片| 在线看片免费人成视频久网下载 | 亚洲成人免费电影| 亚洲免费观看视频| 97在线观看永久免费视频| 青青免费在线视频| 亚洲av丰满熟妇在线播放| 拍拍拍又黄又爽无挡视频免费| 国产精品美女久久久免费 | 麻豆精品成人免费国产片| 亚洲另类精品xxxx人妖|